Data Center Assistant Superintendent
Responsibility Statement
Supervises the field construction of a project as the assistant superintendent including its organization planning and scheduling in order to complete the work on time within budget and to quality specified.
Safety Responsibilities
- Assist in developing and managing the overall site safety program as required and ensuring subcontractor compliance with company standards and all applicable safety codes and regulations.
- Assure the implementation and continuous maintenance of the corporate safety program requirements during the course of the work on a project.
- Ensure subcontractor compliance with company Safety Program and all applicable safety codes and regulations.
- Perform weekly SafetyNet Inspections
- Conduct weekly Critical Safe Behavior Reviews
- Back up for Site Safety Manager and CSA Superintendents on night shift and weekends when required
- Attend participate in daily huddles and trade PTP development
- Ensure that effective reviews of ALL trade PTPs are being conducted and that feedback is being provided promptly to mitigate the occurrence of safety incidents
- Coordinate with Site Safety Manager.
- Maintains a safe and clean project
QA/QC Responsibilities
- Assists with developing and manage the overall site quality program as required and ensuring subcontractor compliance with company standards.
- Assist train and provide oversight for the QA/QC Manager
- Manage the work to ensure that it is installed in compliance with and conforms to the approved contract documents.
- Implement mock-ups and associated testing review and approval.
- Responsible to ensure that mockup/benchmarking are scheduled properly and timely.
- Works with the Engineering Manager to ensure that the level of quality that the documents intend is met so that future reference can be made.
- Monitor the quality and status of the subcontractors construction documents
- Identifies enters tracks and closes QC items
- Reviews mock up list and provides input on required mock-ups
- Inspects ongoing work and work in place using site specific checklists
- Coordinates scheduling of company third party and city inspections through the QCM
- Ensures finished work is protected
- Develops work to complete lists
- Performs final walk through with company and Design Team
- Assist with developing punch list
- Ensure that MEP Cx and other inspections and process are being followed
- Attend Cx Meetings and coordinate related site construction activities
- Responsible for development of the temporary conditioning and enclosure plan in conjunction with the MEP Superintendent
General Responsibilities/Site Specific
- Become fully versed in the requirements of the agreement
- Know the subcontractors scope and contract and changes
- Develop and implement overall project work schedules identifying the critical path including the expediting of scheduled critical materials and equipment for their timely delivery to site.
- Ensure all necessary permits and insurance are in place and kept current for the term of the project. Acting as liaison to inspection agencies.
- Works with the Engineering Manager to ensure that the ROJ log is current and that priorities are communicated across the entire project.
- Works with the BIM manager to ensure that BIM efforts are prioritized and that the BIM schedule is on track and allows for the project schedule to be maintained.
- Implement Daily Construction Reporting (DCR) procedures and assure they are completed per company policy. Actual input may be delegated.
- Ensure that all DCRs from trade contractors are reviewed by staff everyday
- Complete a project level DCR in your own words as to the happenings of the day.
- Place calls to subcontractors to schedule their manpower and start dates for each trade.
- Review the project on a daily basis verify that subcontractor work and labor is correct and is of good workmanship.
- Work with Sr. PMs in the forecasting/monitoring of the General Condition items such as tools cleaning supplies safety masks etc.
- Provide oversight of cleaning and other self-perform operations.
- Review and monitor distribution of RFIs / CSIs / Changes to the field
- Coordinate with Engineering and Controls Managers for SAP management and issuance of changes to the field.
- Responsible for ensuring all superintendents are developing implementing and tracking Weekly Work Plans (WWP) for their areas.
- Provide and ensures all staff are providing weekly schedule updates to the scheduler.
- Ensure that a TEN WEEK LOOK AHEAD for project is being utilized and is updated prior to the subcontractor six week look ahead meetings per meeting schedule.
- Ensure that recovery schedules are being developed and utilized to maintain completion dates
- Responsible for coordination of site logistics.
- Coordinate direct and monitor the activities of subcontractors and suppliers.
- Review and approve subcontractors schedule of values and monthly pay request
- Participate as a Lead in the ORM meeting.
- Participate as a Lead in the OAC meeting.
- Responsible for ensuring all superintendents are scheduling Pull Plans for their areas.
- Ensure all dig permits area being reviewed by VDC team and our team before any excavations occur.
- Perform other duties as needed.
- Ensure that all fragments due to changes are incorporated and accepted in the schedule
- Being an active participant in planning site logistics schedules productions for future builds for the client